document was a detailed estimate of the cost of the works at a total of £6,000. The Committee recommended that the plan be put into execution as soon as practicable, the front line, Meadow ​road​ and Priory street requiring immediate attention. They also recommended the Board to apply for sanction to borrow the £6000 on the credit of the general district rates, to be repaid in 30 years. – Coun. Howell, in moving the adoption of the report, thought it was not possible to come to terms with Mr. Clark, and as the Board had passed a resolution to supply the West Ward with water, they must either rescind that resolution or carry out the works. He then referred to the proposal of bringing water from the Rother, which was undesirable on account of its estimated cost of £12,000, without reckoning the purchase of land, the erection of pumping engines, and the laying of necessary piping in the borough. – Ald. Ginner, in seconding the resolution, did not think it was the best plan that could be adopted, but that it was the best the Board was likely to undertake. He was not one of those who would turn round and walk away becaus(sic) he could not have his own plan carried out. The Board had now an additional means of supply, and had also land whereon they could make reservoirs by the extension of the lease in St. Andrew’s Gardens from 17 to 99 years.

Supply of Pipes. On the recommendation of the Water Committee it was also resolved that the order passed at the previous meeting for contracting with Messrs Cochrane &Co. for twelve months’ supply of water pipes, should be rescinded, as it was found that it was intended to supply Yorkshire iron, instead of Derbyshire iron.

The Government Inspector (Mr. Ranger) having visited Hastings, in consequence of the application for sanction to borrow £6,000, the Water Committee reported at the meeting on the 3rd of August that the Inspector’s opinion was that it was unadvisable to spend money at St. Andrew’s for new reservoirs, and recommended instead the formation of a new distributing reservoir. The Committee concurred in that opinion and recommended that amended particulars should be forwarded to the Secretary of State, asking permission to borrow £7,000. The Committee would select a site and report further as early as possible. – Report adopted.

Sanction Obtained. At the meeting on Sept. 7th the Clerk reported that he had received the sanction to borrow the money, and the Water Committee recommended that the Surveyor be instructed to prepare working plans, sections and specifications for the proposed works, and lay them before the Board at their next meeting. This was agreed to.

Land on the West hill. In answer to Coun. Bromley’s question as to the probability of acquiring land on the West hill for the new reservoir, Mr. Grouse said that he and the Mayor had had an interview with Lady Waldegrave that morning, and it did not appear that any difficulty -